1.A Request for Proposal (RFP) has been received describing the implementation of a centralized data backup solution. The customer has five campus buildings interconnected coaxial Ethernet. Every building has three servers and each server has a 2 GB database that requires nightly backup. The backups must be completed in a fourhour window. A technical staff person attending an IBM road show heard about IBM Tivoli Storage Manager (ITSM) and is considering implementing this solution. What is the next step to be performed by a Business A.Call IBM TechLine/PartnerLine to provide the solution B.Commit to a six week trial of an integrated solution C.Contact Tivoli for an analysis and software quote D.Engage a technical specialist to develop a solution Correct 2.A customer is using Fast Dump Restore (FDR) to do vaulting and is sending 500 ECCST tapes offsite each day. The customer is upgrading to IBM 3590E1A drives from IBM 3490/36 track technology. Which of the following indicates the minimum number of "J" cartridges, assuming maximum utilization of the capacity of the cartridges, that the customer would send offsite each 3.A Data Center manager would like to reduce operational storage management requirements. They currently have an IBM eServer zSeries, several IBM eServer pSeries, and multiple nonIBM UNIX servers installed. Each system uses a unique backup tool with various types of tape systems. Which of the following would be the most complete solution to simplify operations and reduce storage management costs? A.Use CA Unicenter to backup all installed servers. B.Use Tivoli Storage Manager and DFSMShsm to provide backup of supported servers. C.Install Tivoli Storage Manager to provide backup services for supported servers. D.Install Tivoli Storage Manager for zSeries. 4.A customer is experiencing poor performance on their VTS for some of their batch tape jobs. Which of the following IBMTools jobs should be run to help determine the nature of the problem? Correct 5.A customer is using Tivoli Storage Manager (TSM) on an IBM eServer zSeries system connected to their IBM TotalStorage Virtual Tape Server (3494) and six native IBM 3590E drives connected via ESCON. They want to migrate their TSM workload onto an IBM eServer pSeries system. After it is moved, TSM will require the use of two drives. They asked the IBM Storage Specialist for a recommendation on how to connect the required two drives. Which of the following should be A.Connect two ESCON drives to the pSeries ESCON card. B.Direct connect two drives to the pSeries server. in the IBM 3494 Library for TSM to use. D.Convert two 3590 drives to FICON and then attach them to the pSeries system. 6.A customer utilizes DFSMShsm migration level 2, and has 10000 3490E extended length cartridges. How many 3592 300GB cartridges would be required for this amount of data? 7.The IBM Magstar 3590 drives are attached to an IBM Magstar 3590 ESCON controller. Which of the following parameters will have the LEAST effect on the overall throughput performance? 8.A customer has a 3494B20 tape drives housed in a 10 frame 3494 library. The 3494 is running out of slots for stacked volumes. What can be added to reduce the number of stacked volumes, and increase the performance of the back end? 9.A tape marketing specialist is asked to determine the number of cartridge slots currently under STK silo automation. Which of the following would give the key information necessary to A.The number of installed Timberline drives (9490) B.The number of installed Library Storage Modules (LSM) C.The number of installed Library Management Units (LMU) D.The number of installed Automated Cartridge Systems (ACS) 10.A hospital has an IBM eServer zSeries platform and wants to start digitizing all patient files. They plan to store patient files online for the first six months and then move them to a tape library. Which of the following tools should be recommended? |